October 4, 2021 – Doors installed

We woke up to a cool morning, with temperatures during the day getting up to the mid-seventies …. great working weather!    After our devotion and prayer, Bob handed us a FULL sheet with our tasks for the day (typically our tasks fit on a half of a sheet of paper).    

The first task for everyone was to unpack the kitchen cabinets and use the cardboard to protect the floor.  We taped the cardboard 3-4″ away from all of the walls to allow room for the molding.

While we were taping, the kitchen team was starting to layout the placement  of the cabinets.   They then mounted the wall and base cabinets.   The kitchen is certainly coming together!

There was another team working on installing the door case trim.  They started with the front and back door, and then moved into the bedrooms.

Joe and I were on one of the door crews.    After a refresher from Bob, we were able to install the door to one of the bedrooms, and the door to the bathroom.   The other door teams were hard at work.  By the end of the day, we had all the doors installed!

I’m thinking that floor trim is on the agenda for tomorrow ;-).  

 

3 Replies to “October 4, 2021 – Doors installed”

  1. You don’t miss a thing. The door frame detail looks terrific . The kitchen cabinets are better than those in most homes. Everything is coming together. It’s truly a spectacular home. All who are following this have to be more than a little envious.

Leave a Reply to Debbie Cancel reply

Your email address will not be published. Required fields are marked *